    Physical and Financial Progress Record of MPWSRP Contracts [MINOR]
Note. : Physical and Financial Progress Record of On-Going MPWSRP contract..
" Executed Quantity" : in RED indicates, recording is not yet done for current month [MAR].
S.No. Name of Basin Division Package No. Scheme Name Work Name Contract Status Contract No Contract Amount Date Of Agreement Date Of Completion Contractor Name Item Of Work Agreemented Quantity Progress as on month MAR
Executed Quantity Physical
( %)
Financial Expenditure (Lakh) Financial
( %)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
1. Chief Engineer Chambal Betwa Basin, Bhopal Samrat Ashok Sagar Division No. 2 Vidisha NA Ghosua Tank Ghosua Complete VID-185 48.89 03/03/2014 02/03/2015 Ghosua WUA Pitching 1388.73 1314.88 95 4.42
Earthwork 29745.88 22616 76 11.81
Others 0 0 0 3.76
RCC and PCC 612.64 340.41 56 9.13
Total 57 29.12 60
2. Chief Engineer Chambal Betwa Basin, Bhopal Samrat Ashok Sagar Division No. 2 Vidisha NA Phupher Minor Phupher Minor Complete VID-186 48.89 03/03/2014 02/03/2015 Phupher WUA Earthwork 14374.88 4283 30 3.85
RCC and PCC 588.26 50.1 9 2.11
Pitching 1133.7 1050 93 5.5
Others 0 0 0 0.99
Total 33 12.45 25
3. Chief Engineer Chambal Betwa Basin, Bhopal Sanjay Sagar Project Bah River Division Ganjbasoda NA Bhavankhedi Bhavankhedi Complete VID-188 48.89 03/03/2014 02/03/2015 Bhavankhedi WUA Earthwork 15084 21565 100 11
Others 0 0 0 4
RCC and PCC 613.46 185.38 30 4.17
Pitching 1158 235.05 20 2.83
Total 38 22 45
4. Chief Engineer Chambal Betwa Basin, Bhopal Sanjay Sagar Project Bah River Division Ganjbasoda NA Ghatera Babaji Ghatera Babaji Complete VID-187 48.89 03/03/2014 02/03/2015 Ghatera Babaji WUA RCC and PCC 256.69 216.69 84 5.61
Earthwork 20545 19545 95 25.29
Others 0 0 0 3.1
Pitching 1911 1500 78 4
Total 64 38 78
5. Chief Engineer Chambal Betwa Basin, Bhopal Water Resources Division Ashoknagar NA Fatehabad Fatehabad On Going ASH-47 11.8 30/08/2014 30/06/2015 Fatehabad WUA Earthwork 2150.63 915.52 43 1.04
Concrete Masonry 0 40.3 0 0.96
Pitching-B.Toe 0 61.16 0 0.2
Total 14 2.2 19
6. Chief Engineer Chambal Betwa Basin, Bhopal Water Resources Division Ashoknagar NA RAMNAGAR RAMNAGAR On Going ASH-46 30.3 30/08/2014 30/06/2015 RAMNAGAR WUA Others 1.28 0 0 1.28
Earthwork 8280.66 2103.13 25 2.35
Concrete Masonry 767.19 320.86 42 5.35
Total 22 8.98 30
7. Chief Engineer Chambal Betwa Basin, Bhopal Water Resources Division Ashoknagar NA Amahi Dam Restructuring and modernization of amahi Complete ASH-18 196.46 01/12/2012 28/02/2014 Rajlaxmi Constn.Co.Guna Concrete Masonry 1683.23 1651 98 45.9
Pitching 9205.76 8619.9 94 33.32
Road Work 0 0 0 0
Others 0 0 0 44.43
Lining all type 967.4 898.4 93 38.7
Earthwork 42667.82 37742 88 18.91
Total 62 181.26 92
8. Chief Engineer Chambal Betwa Basin, Bhopal Water Resources Division Ashoknagar NA Bharoli Dam Restructuring and Modernization of Head Works and Canals of Bharoli Tank On Going ASH-25 73.67 19/06/2013 18/06/2015 MAA VAISHNO BUILDERS Others 0 23 0 0.55
Earthwork 13287.6 11678 88 3.39
Pitching-B.Toe 3073.7 2026.3 66 6.73
Lining all type 511.6 50 10 2
Masonary 1010.1 650 64 22.18
Total 46 34.85 47
9. Chief Engineer Chambal Betwa Basin, Bhopal Water Resources Division Ashoknagar NA Jamakheri Dam Restructuring and Modernization of Jamakhedi Tank. On Going ASH-19 175.06 17/04/2013 17/04/2015 Rajlaxmi Constn.Co.Guna Earthwork 43857 19404.27 44 14.06
Others 0 0 0 16.64
Pitching 18349.71 5411.4 29 20.32
Concrete Masonry 149.81 133 89 3.25
Lining all type 959.94 165.69 17 6.25
Total 36 60.52 35
10. Chief Engineer Chambal Betwa Basin, Bhopal Water Resources Division Ashoknagar NA Kadwaya Restructuring and Modirnization of Kadwaya Munderi Tank Complete ASH-7 49.33 25/05/2011 24/05/2012 Rajlaxmi Constn.Co.Guna Lining all type 282 239 85 7.91
Earthwork i/c CNS 24810 16443 66 9.73
Concrete Masonry 0 0 0 0
Gates 0 0 0 0
Concrete 0 0 0 0
Pitching-B.Toe 1216 1216 100 6.84
Others 0 0 0 5.71
Total 36 30.19 61
11. Chief Engineer Chambal Betwa Basin, Bhopal Water Resources Division Ashoknagar NA Sajanmau Restructuring and Modirnization of Sajanmau Umariya Tank Complete ASH-11 310.46 28/08/2010 27/08/2012 Bhagwat Prasad Sharma Gwalior Lining all type 2252.65 2485.14 100 68.61
Concrete Masonry 3065.55 3276 100 102.01
Pitching-B.Toe 13828.84 599 4 14.83
Others 0 13769 0 48
Earthwork i/c CNS 131881.8 130088 99 91.38
Total 61 324.83 105
12. Chief Engineer Chambal Betwa Basin, Bhopal Water Resources Division Ashoknagar NA Sakarra Restructuring and Modirnization of Sakarra Tank Complete ASH-12 35.65 27/04/2011 26/04/2012 Rajlaxmi Constn.Co.Guna Others 4.29 0 0 1.5
Concrete 381 297 78 10.43
Earthwork i/c CNS 7346 7184 98 5.76
Lining all type 307 307 100 13.73
Total 69 31.42 88
13. Chief Engineer Chambal Betwa Basin, Bhopal Water Resources Division Ashoknagar NA Singhpur chalda Singhpur chalda On Going ASH-44 11.2 30/08/2014 30/06/2015 Singhpur chalda WUA Concrete Masonry 0 7 0 0.42
Earthwork 6728.97 659.97 10 0.75
Total 5 1.17 10
14. Chief Engineer Chambal Betwa Basin, Bhopal Water Resources Division Ashoknagar NA Tulsi sarovar Tulsisarovar & Pachadikheda Complete ASH-20 51.66 21/02/2011 20/02/2012 A.K.Shivhare Pvt. Ltd. Pitching-B.Toe 5065 3435 68 10.48
Others 0 0 0 5.39
Earthwork 11350 8535 75 3.26
Lining all type 310 281.5 91 11.3
Total 58 30.43 59
15. Chief Engineer Chambal Betwa Basin, Bhopal Water Resources Division Ashoknagar NA Vikrampur Vikrampur On Going ASH-45 29.3 30/08/2014 30/06/2015 Vikrampur WUA Earthwork 5233.12 1347.77 26 1.29
Concrete Masonry 0 52 0 1.25
Total 13 2.54 9
16. Chief Engineer Chambal Betwa Basin, Bhopal Water Resources Division Bhopal NA Garethia Dam RESTRUCTINING & MODERNIZATION OF HEAD WORK AND CANALS OF GERATIA & KARONDIYA TANK, BHOPAL (CB-25) Complete BHO-21 466.73 24/08/2013 23/07/2015 Ramnarayan Const. Bikaner (Raj.) Pitching 14001.41 13812.42 99 41.55
RCC and PCC 2.17 3027.94 100 0.13
Lining all type 104.58 103.01 98 5.31
Jungle Clearance 35250 34530 98 0.15
Lining all type Repair of Structures 4572 4676.03 100 20.48
Moorum Topping 1680 1599.53 95 3.33
Concrete 471.37 471.21 100 25.45
Dismantling 331.41 223.04 67 0.39
Boundary Stone 1271 1270 100 5.28
UCR 1:3:6 (Uncorsed rubble masonary) 3767.12 3766.26 100 125.97
Earthwork 19517.45 120154.07 100 24.98
CC 1:2:4 2018.25 2016.97 100 74.41
Miscellenious 2243.38 2237.37 100 5.77
NP3 Pipe 109 87.5 80 3.39
NP2 Pipe 10 30 100 1.17
Others 45384.8 41349.25 91 6.02
Excavation 97321.85 97153.17 100 101.92
Lining CC 1 2 4 54.86 54.8 100 2.61
Colaba 47 47 100 1.32
Flush Pointing 1680.12 1677.72 100 1.23
Gates 4.95 4.92 99 1.04
CC 1:3:6 146.19 145.98 100 4.32
CNS 468 463.9 99 1.83
Turfing 19600 19570 100 4.11
Tamping 6329.26 5696.56 90 0.85
Stripping 1429.8 1423.67 100 0.57
Steel 35393.93 33726.12 95 18.89
Total 97 482.47 103
17. Chief Engineer Chambal Betwa Basin, Bhopal Water Resources Division, Guna NA Mohari Tank Restructuring and Modernisation of Mohari Tank Complete GUN-26 146.31 15/04/2013 14/04/2015 Dwarikadheesh Const. Gwalior RCC and PCC 694 280 40 12.5
Masonary 0 210.78 0 7.32
Pitching 2233 2150 96 12.54
Lining all type 1185 1450 100 75.29
Earthwork 42613 48996 100 41.64
Total 67 149.29 102
18. Chief Engineer Chambal Betwa Basin, Bhopal Water Resources Division, Narsinghgarh NA Baiheda Baiheda Complete RAJ-134 27.51 03/02/2014 02/12/2014 Baiheda WUA Earthwork 12709.52 2606.37 20 2.19
RCC and PCC 220.12 0 0 0
Lining all type 166.35 0 0 0
Pitching 687.6 0 0 0
CNS 539.78 0 0 0
Masonary 0 0 0 0
Total 3 2.19 8
19. Chief Engineer Chambal Betwa Basin, Bhopal Water Resources Division, Narsinghgarh NA Malawar Malawar Complete RAJ-133 35.24 03/02/2014 02/12/2014 Malawar WUA Masonary 45.08 0 0 0
Pitching 848.85 800 94 0
Lining all type 403.82 45.68 11 0
Earthwork 21015.05 7910.88 38 4.28
CNS 1168.06 472.5 40 0
RCC and PCC 189.78 74.15 39 0
Total 37 4.28 12
20. Chief Engineer Chambal Betwa Basin, Bhopal Water Resources Division, Narsinghgarh NA Shamsherpura Modernisation of H/W and Canal of Shamsherpura Tank. Terminate RAJ-37 216.17 16/12/2010 15/12/2011 Govind Construction Co.Gwalior Earthwork i/c CNS 200530 194850.15 97 185.41
Lining all type 1121 935.22 83 0
Repair of Structure 0 923 0 0
Others 37.31 25.81 69 0
Concrete Masonry 1230 935.22 76 0
Gates 3.17 0 0 0
Pitching 728 702 96 0
Total 60 185.41 86
21. Chief Engineer Chambal Betwa Basin, Bhopal Water Resources Division, Narsinghgarh NA Agar Agari Dam Restructing and modernization of Head Work and Canal of Agar-Agri Tank. Complete RAJ-101 157.21 30/01/2014 29/06/2015 Radheshyam Sondhiya Pitching 1756.81 1750 100 0
Masonary 405.82 224 55 0
Lining all type 8148 6832 84 0
Gates 3.05 0 0 75.96
Earthwork 72460.71 57955 80 0
CNS 3401.73 1556.4 46 0
RCC and PCC 1113.36 705.85 63 0
Total 61 75.96 48
22. Chief Engineer Chambal Betwa Basin, Bhopal Water Resources Division, Narsinghgarh NA Napanera Restructuring and modelization of H/W and canal Complete RAJ-78 143.34 05/08/2013 04/07/2015 Radheshyam Sondhiya Gates 2.7 0 0 0
Masonary 15.81 0 0 0
Lining all type 795.93 661.42 83 0
Earthwork i/c CNS 52448.59 31372 60 100.93
RCC and PCC 1834.93 1385 75 0
Total 44 100.93 70
23. Chief Engineer Chambal Betwa Basin, Bhopal Water Resources Division, Narsinghgarh NA Banda Bedra Dam Restructuring and modernization of Head work and canal of Banda-bendra and hedapura Tank. Complete RAJ-99 236.56 12/12/2013 11/08/2015 Ajay Jain Datiya Earthwork i/c CNS 60484 43227 71 144.01
Pitching 1021.94 962 94 0
Masonary 1627.92 1755 100 0
Lining all type 1095 710 65 0
RCC and PCC 1096 600 55 0
Total 77 144.01 61
24. Chief Engineer Chambal Betwa Basin, Bhopal Water Resources Division, Narsinghgarh NA Jamuniya Rao Dam Restructuring and modernization of head work and canals of Jamunia Rao and Tinonia Tank. Complete RAJ-104 161.81 04/03/2014 03/06/2014 Gyasiram Kushwah Gwalior Pitching 7427 6220 84 0
Masonary 754 673 89 0
Lining all type 73 700 100 0
Earthwork 61725 48450 78 105.61
RCC and PCC 278 282 100 0
Total 90 105.61 65
25. Chief Engineer Chambal Betwa Basin, Bhopal Water Resources Division Raghogarh NA Barod Dam Restructuring and modernization of Head Work & Canal Complete GUN-34 179.83 15/07/2013 14/07/2015 Chandrhas Sharma Pitching-B.Toe 1647 1283.2 78 6.43
Others 0 0 0 0
Lining all type 1443.46 1392.36 96 63.17
Earthwork 45154.95 42067.1 93 34.14
Concrete Masonry 591.12 18765 100 19.71
Road Work 0 0 0 0
Total 61 123.45 69
26. Chief Engineer Chambal Betwa Basin, Bhopal Water Resources Division Raisen NA Makhani Dam Restructuring and Modernization for Makhani Complete RAI-27 74.55 07/05/2011 12/08/2012 Patel and Associates, Bhopal Others 13.92 0 0 25.36
Pitching 566 668.14 100 3.4
Lining all type 486 588.53 100 28.32
Earthwork 52178 52757.15 100 21.36
Total 75 78.44 105
27. Chief Engineer Chambal Betwa Basin, Bhopal Water Resources Division Raisen NA Bancchod Restructuring and Modernization of Banchod Tank & its Canal. Complete RAI-23 476.44 30/12/2009 03/02/2012 VIJAY KUMAR MISHRA Gates 0 0 0 0
Pitching 2850 2850 100 12.8
Lining all type 4895 4895 100 164
Others 58.01 0 0 35
Concrete 2455 2455 100 67.5
Earthwork i/c CNS 171630 171636 100 98.5
Total 67 377.8 79
28. Chief Engineer Chambal Betwa Basin, Bhopal Water Resources Division Raisen NA Sudra Dam Restructuring and Modernization of Head Work and Canals of Sudra Tank Complete RAI-52 85.94 19/09/2013 18/07/2015 Ayaj Ali,Raisen Earthwork 26361 26361 100 19.12
RCC and PCC 1107 1107 100 50.82
Others 0 0 0 3.76
Pitching 1004 1048 100 3.8
Total 75 77.5 90
29. Chief Engineer Chambal Betwa Basin, Bhopal Water Resources Division Raisen NA Chandana Restructuring and Modernization of Head works and Canals of Chandana tank Complete RAI-51 70.94 06/05/2013 05/05/2015 Ayaj Ali,Raisen Earthwork 30890 30890 100 27.45
Pitching 3026.86 3026 100 11
RCC and PCC 645.35 645 100 24.12
Others 0 0 0 4.71
Total 75 67.28 95
30. Chief Engineer Chambal Betwa Basin, Bhopal Water Resources Division Raisen NA Karmodia Dam Restructuring and Modernization of Karmodia Tank for Complete RAI-29 275.36 31/12/2010 03/02/2012 VIJAY KUMAR MISHRA Others 26.82 0 0 5.29
Lining all type 2414 2545.75 100 96.82
Pitching 816 816 100 3.83
Earthwork i/c CNS 34280 34326.48 100 16.7
Total 75 122.64 45
31. Chief Engineer Chambal Betwa Basin, Bhopal Water Resources Division Raisen NA Ratapani Dam Restructuring and Modernization of Ratapani Tank and canal Complete RAI-25 641.27 19/02/2010 18/02/2012 VIJAY KUMAR MISHRA Lining all type 6060 6678 100 238.31
Others 211.87 0 0 118.81
Earthwork i/c CNS 260000 241135 93 189.85
Pitching 2100 2377 100 11.31
Total 73 558.28 87
32. Chief Engineer Chambal Betwa Basin, Bhopal Water Resources Division Raisen NA GULGAOWN Restructuring & Modernization of GULGAON Tank Complete RAI-37 42.46 04/02/2010 03/02/2011 Vigyashree Infrastructures Bhopal Gates 0 0 0 0
Concrete 147.44 115.04 78 3.14
Lining all type 221.14 245.76 100 11.06
Others 5.29 0 0 1.65
Pitching 5403 3735.63 69 13.83
Earthwork i/c CNS 5363.17 5056.75 94 2.97
Total 57 32.65 77
33. Chief Engineer Chambal Betwa Basin, Bhopal Water Resources Division Raisen NA Dahod Restructuring & Modernization Work of Dahod & Dhamdhusar Tanks and Canal Complete RAI-22 772.72 08/02/2010 07/12/2012 Vigyashree Infrastructures Bhopal Pitching 11000 11117 100 35.09
Lining all type 11300 11729 100 485.14
Others 136.95 0 0 135.01
Gates 0 0 0 0
Earthwork i/c CNS 207900 171865 83 80.79
Repair of Structure 0 0 0 0
Total 47 736.03 95
34. Chief Engineer Chambal Betwa Basin, Bhopal Water Resources Division Rajgarh NA Kasturipura Dam Restructiong of modernization of head work and canal Kasturipura sanwasara and kolukhedi tank Complete RAJ-96 127.9 06/06/2013 05/06/2015 Shubham Construction Rajgarh Lining all type 567.99 551.72 97 23.45
Masonary 0 210.78 0 17.45
Earthwork 54925.46 38048.19 69 20.86
RCC and PCC 1668.08 1760.06 100 48.02
Pitching 3198.68 2742.23 86 12.54
Total 70 122.32 96
35. Chief Engineer Chambal Betwa Basin, Bhopal Water Resources Division Rajgarh NA Amanpura Dam Restructiong of modernization of head work and canals Amanpur and Deopur Tank Complete RAJ-95 121.25 03/07/2013 03/07/2015 Surendra singh Sisodiya Rajgarh Lining all type 349.52 374.97 100 16.33
Masonary 22.8 0 0 9.37
Pitching 3085 2399.56 78 3.17
RCC and PCC 1668.08 1111.85 67 32.21
Earthwork 37198.42 30647.74 82 23
Total 65 84.08 69
36. Chief Engineer Chambal Betwa Basin, Bhopal Water Resources Division Sehore NA Gyaraspura Dam Gyaraspura Dam Complete SEH-92 48.1 18/02/2014 31/03/2015 GYARASPURA WUA RCC and PCC 536 90 17 3
Earthwork 10923 12000 100 8.4
Lining all type 350 410 100 14.45
Others 0 0 0 5.22
Pitching 3937 3900 99 19.25
Total 63 50.32 105
37. Chief Engineer Chambal Betwa Basin, Bhopal Water Resources Division Sehore NA Maina I Tank Restructuring and modernizationmaina-1 guradi rupchand and bhoura On Going SEH-81 99.93 02/11/2014 06/10/2015 Public Relation Construction Co. Lining all type 248.95 80 32 9
Others 0 0 0 2.52
Pitching 5725.37 5232 91 20
RCC and PCC 203.73 180 88 6
Earthwork 51780 48298 93 47
Total 61 84.52 85
38. Chief Engineer Chambal Betwa Basin, Bhopal Water Resources Division Sehore NA Moondla Dam Restructuring & Modernization of H/w & Canal of Moodla Dam Complete SEH-97 82.35 16/06/2013 09/06/2015 Public Relation Construction Co. Earthwork 58007.7 56341 97 82.05
RCC and PCC 598.34 163 27 0
Others 0 0 0 0
Lining all type 1589 1320 83 0
Pitching 362.03 398.23 100 0
Total 61 82.05 100
39. Chief Engineer Chambal Betwa Basin, Bhopal Water Resources Division Sehore NA Jamuniya Tank Restructuring work of jamonia & khaikheda Complete SEH-80 211.99 11/02/2014 10/05/2015 Public Relation Construction Co. Earthwork 129131 135495 100 75.86
Others 0 0 0 2.5
Pitching 610.11 444 73 1.58
RCC and PCC 2358.1 436 18 10.14
Lining all type 7675 1610 21 23.96
Total 42 114.04 54
40. Chief Engineer Dhasan Ken Basin, Sagar Water Resources Division, Damoh NA Gadaghat Dam Restructuring of Chiraipani Jabera and Gadaghat Tanks Complete DAM-60 1172.39 29/01/2010 15/06/2012 NAVBHARAT BUILDCON KISHANGARH RAJASTHAN Others 0 0 0 88.44
Earthwork i/c CNS 452395 451384 100 285.28
Lining all type Repair of Structures 19085 19312 100 695.05
Gates 0 0 0 0
Pitching-B.Toe 17396 15444 89 50.52
Total 58 1119.29 95
41. Chief Engineer Dhasan Ken Basin, Sagar Water Resources Division, Damoh NA Majhagawan hansraj Restructuring of Majhgawan hansraj tank Complete DAM-80 129.64 24/11/2012 23/02/2014 Keshri Const. Panna Others 0 0 0 15.55
Pitching 4664 4821 100 31.34
Lining all type Repair of Structures 1520 601 39 23.85
Earthwork i/c CNS 11733 8498 72 13.21
Total 53 83.95 65
42. Chief Engineer Ganga Basin, Rewa Purwa Canal Division No.2 Satna NA Loni Dam Rest.andMod. Loni Tank On Going REW-55 119.49 30/04/2012 30/04/2013 RAVI CONSTRUCTION COMPANY Others 0 0 0 8.46
Lining all type 853.11 759.8 89 26.97
Jungle Clearance 103700 103830 100 0.52
Earthwork 124185.7 122500 99 67.39
Pitching 1250 1244.86 100 20.77
Total 77 124.11 104
43. Chief Engineer Ganga Basin, Rewa Upper Purwa Canal Division Rewa NA Govindgarh Dam Rest.andMod.Govindgarh Tank On Going REW-56 216.19 30/04/2012 30/04/2013 Dayal Engg. Dismantling 724.8 0 0 0
Steel 62499.38 64499.83 100 25.68
Pitching 2150.86 2150.85 100 2.9
Others 0 0 0 2.9
Earthwork 50429.55 50429.55 100 43.24
Concrete 1321.31 1444.62 100 59.7
Excavation 4957.77 0 0 0
Total 57 134.42 62
44. Chief Engineer Ganga Basin, Rewa Upper Purwa Canal Division Rewa NA Atari Dam restructuring work of atari and kanhaiya dam On Going REW-123 234.81 06/05/2013 05/05/2015 SHIVSHAKTI CONSTRUCTION COMPANY Others 0 0 0 5.23
Concrete 1378.54 771.08 56 21.86
UCR 1:3:6 (Uncorsed rubble masonary) 1300.448 306.36 24 5.81
Lining all type 755.16 0 0 0
Pitching 5159.36 6046.97 100 34.54
Earthwork 49957.82 15507.51 31 5.5
Total 35 72.94 31
45. Chief Engineer Ganga Basin, Rewa Water Resources Division Satna NA AMRANALLA AMRANALLA Weir On Going SAT-46 18.19 06/07/2013 05/05/2014 Neelkanth WUA Gates 2 2 100 0.45
Repair of Structure 4 1 25 0.28
Others 0 0 0 0
Earthwork 3150 2795.47 89 0.84
Lining all type 250.31 182.19 73 7.13
Earthwork i/c CNS 8463.37 1382.26 16 1.43
Total 50 10.13 56
46. Chief Engineer Ganga Basin, Rewa Water Resources Division Satna NA Amua Dam Amua Tank On Going SAT-49 39.4 09/12/2013 08/10/2014 Amua WUA Repair of Structure 3 3 100 2.25
Lining all type 403.1 479.98 100 20.44
Gates 0 0 0 0
Earthwork 16068.28 15748 98 6.29
Pitching-B.Toe 960.06 1088.12 100 9.08
Others 0 0 0 2.39
Total 66 40.45 103
47. Chief Engineer Ganga Basin, Rewa Water Resources Division Satna NA Asrar Dam Asrar Tank On Going SAT-52 49.81 10/12/2013 09/10/2014 Asrar WUA Gates 0 0 0 0
Lining all type 0 0 0 0
Others 0 0 0 0
Earthwork 7500 6200 83 3.49
Repair of Structure 2 2 100 44.95
Pitching-B.Toe 121 121.15 100 1.25
Total 47 49.69 100
48. Chief Engineer Ganga Basin, Rewa Water Resources Division Satna NA Chithara Dam Chithara Tank On Going SAT-51 49.86 10/12/2013 09/10/2014 Chitahara WUA Gates 1 201 100 1.14
Lining all type 201.78 279.89 100 6.42
Repair of Structure 4 153 100 20.2
Others 0 0 0 0
Pitching-B.Toe 1497.05 1541.6 100 19
Earthwork 32505.02 32716.74 100 52.83
Total 83 99.59 200
49. Chief Engineer Ganga Basin, Rewa Water Resources Division Satna NA KHUTAHA Khutha Weir SAT-50 15.09 10/12/2013 09/10/2014 Chidawad WUA Lining all type 97.55 136.77 100 8.4
Earthwork 4008.83 4213.63 100 9.3
Repair of Structure 8 181 100 14.4
Pitching-B.Toe 12.58 212.58 100 4.17
Others 0 0 0 0
Gates 1 201 100 0
Total 83 36.27 240
50. Chief Engineer Ganga Basin, Rewa Water Resources Division Satna NA Kirhai Kirhai Tank On Going SAT-47 11.67 11/09/2013 10/07/2014 Asrar WUA Earthwork 4522.5 4601 100 5.94
Concrete 107.1 106.8 100 4.9
Total 100 10.84 93
51. Chief Engineer Ganga Basin, Rewa Water Resources Division Satna NA KOTHI KOTHI Weir Complete SAT-48 36.28 01/10/2013 31/07/2014 Kothi WUA Gates 1 1 100 0.42
Earthwork 20102 18977 94 10.1
Pitching-B.Toe 207 0 0 0
Repair of Structure 12 12 100 4.07
Others 0 0 0 4.3
Lining all type 181 308.5 100 13.22
Total 66 32.11 89
52. Chief Engineer Ganga Basin, Rewa Water Resources Division Satna NA Lilgee Reservoir Dam Restructuring and Modernisation of Lilgee Tank On Going SAT-45 115.49 31/12/2013 31/08/2015 Mishra Brothers Etawa Earthwork 43232.6 20269.58 47 5.34
Pitching 1549 0 0 0
Repair of Structure 66 31 47 1.86
Lining CC 1 2 4 1501.97 839 56 37.78
Total 37 44.98 39
53. Chief Engineer Ganga Basin, Rewa Water Resources Division Satna NA JAMUNIHAI Restructuring and Modernization of Head works and Canals of Jamunihai Weir and Bhaiswar Tank On Going SAT-44 221.71 22/05/2013 21/05/2015 Mahendra Kumar Mishra UCR 1:3:6 (Uncorsed rubble masonary) 623 433.41 70 10.48
Gates 1000 0 0 0
Pitching 198.45 0 0 0
CC 1:2:4 345.19 257.8 75 9.23
Lining all type 2371 2162.92 91 134.03
Earthwork 138061 78195 57 2.61
Others 0 0 0 13.37
Total 42 169.72 77
54. Chief Engineer Ganga Basin, Rewa Water Resources Division Satna NA Singhpur Dam restructuring & modernisation of Singhpur and Chidua tank On Going SAT-38 312.59 22/04/2013 23/10/2014 Maa Sherawali & Co. , Satna Steel 169.7 169.7 100 0.08
Pitching 496 494.3 100 3.37
Moorum Topping 0 0 0 0
Lining all type 4791.6 4780 100 202.07
Earthwork 51710.39 51700 100 67.15
Repair of Structure 3 3 100 2.4
CC 1:2:4 537.45 530 99 17.7
RCC and PCC 1.9 1.9 100 0.09
Others 0 0 0 2.09
Total 78 294.95 94
55. Chief Engineer Ganga Basin, Rewa Water Resources Division Satna NA Berahna Restructuring of Birhana tank and canal On Going SAT-53 186.48 28/02/2014 31/05/2015 Maa Sherawali & Co. , Satna No. of Structure 290 165 57 40.79
Lining all type 11366 11366 100 58.39
Pitching 1194.93 1194.93 100 10.81
Earthwork 65470 90321.2 100 68.42
Total 89 178.41 96
56. Chief Engineer Ganga Basin, Rewa Water Resources Division Satna NA CHAMARA Restructuring of Chamara weir its canal & Structures Complete SAT-36 9.9 01/12/2012 31/05/2013 Chitahara WUA Repair of Structure 2 2 100 1.67
Others 1.16 1.26 100 1.26
Earthwork i/c CNS 3151.75 3465 100 0.93
Gates 0.477 0.48 100 0
Lining all type 168.21 185.1 100 5.53
Total 100 9.39 95
57. Chief Engineer Ganga Basin, Rewa Water Resources Division Satna NA JHURA NALLA Restructuring of Jhoora nala weir & its structures Complete SAT-37 17.88 01/12/2012 31/05/2013 Hanuman WUA Others 16.48 16.48 100 0.75
Lining all type 226.22 124.68 55 5.07
Earthwork i/c CNS 4738.3 3310 70 3.88
Repair of Structure 1.89 1 53 0.05
Pitching-B.Toe 0 0 0 0
Gates 3 3 100 0.44
Total 63 10.19 57
58. Chief Engineer Ganga Basin, Rewa Water Resources Division Satna NA NIMI Restructuring of Nimi weir & its structures Complete SAT-35 9.55 01/12/2012 31/05/2013 Matehna WUA Earthwork i/c CNS 6299 5538 88 1.44
Lining all type 98.25 76.28 78 2.24
Gates 2 2 100 0.6
Others 0 0 0 1.37
Pitching-B.Toe 4.46 0 0 0
Repair of Structure 4 3 75 1.15
Total 57 6.8 71
59. Chief Engineer Narmada Tapti Basin, Indore Water Resources Division Dewas NA Aghera Aghera Tank On Going DEW-28 31.6 01/10/2013 30/09/2014 Momanp WUA Concrete 595.2 435.18 73 23.6
Earthwork 17362 13362 77 0
Total 75 23.6 75
60. Chief Engineer Narmada Tapti Basin, Indore Water Resources Division Dewas NA Amlawati Amlawati Tank On Going DEW-23 47.4 01/10/2013 30/09/2014 Sindhani WUA Concrete 184 65 35 0
Earthwork 29425 20991 71 29.21
Total 53 29.21 62
61. Chief Engineer Narmada Tapti Basin, Indore Water Resources Division Dewas NA Bhutia Nall T. Dam Bhutia Tank On Going DEW-27 31.7 01/10/2013 30/09/2014 Pipalrawan WUA Earthwork 59540 25810 43 0
Concrete 493 67.62 14 16.6
Total 28 16.6 52
62. Chief Engineer Narmada Tapti Basin, Indore Water Resources Division Dewas NA Chidawad Chidawad Tank On Going DEW-26 32.6 01/10/2013 30/09/2014 Chidawad WUA Concrete 263 184.98 70 0
Earthwork 31655 36360.88 100 30.06
Total 85 30.06 92
63. Chief Engineer Narmada Tapti Basin, Indore Water Resources Division Dewas NA Mendia Mendia Tank On Going DEW-22 33.3 01/10/2013 30/09/2014 Momanp WUA Earthwork 24576 25080 100 0
Concrete 55 13.73 25 27.02
Total 62 27.02 81
64. Chief Engineer Narmada Tapti Basin, Indore Water Resources Division Dewas NA Momanpura Dam Momanpura Tank On Going DEW-29 106.58 22/06/2013 21/06/2015 Navbharat Buildcon Earthwork 49933 56606 100 0
Concrete 1534.3 1316 86 103.8
Total 93 103.8 97
65. Chief Engineer Narmada Tapti Basin, Indore Water Resources Division Dewas NA Nagda Gajora Nagda Tank On Going DEW-30 153.59 22/06/2013 21/06/2015 PRAGATI CONSTRUCTION DEWAS Earthwork 57840 58306 100 0
Concrete 637 566.56 89 143.33
Total 94 143.33 93
66. Chief Engineer Narmada Tapti Basin, Indore Water Resources Division Dewas NA Lakumadi Restructuring of Lakumadi On Going DEW-9 16.27 08/01/2013 18/06/2013 Pipalrawan WUA Earthwork 17134 18798 100 0
Concrete 145.61 276.84 100 24.17
Total 100 24.17 149
67. Chief Engineer Narmada Tapti Basin, Indore Water Resources Division Dewas NA Patadi Restructuring of Patadi Project On Going DEW-13 31.07 06/05/2013 05/03/2014 Nagda WUA Earthwork 32677.46 34524 100 30.32
Concrete 155.62 130.2 84 0
Total 92 30.32 98
68. Chief Engineer Narmada Tapti Basin, Indore Water Resources Division Dewas NA Pipalrawa Restructuring of Pipalrawa Project On Going DEW-10 48.86 30/10/2012 15/07/2013 Pipalrawan WUA Earthwork 24928.74 24928.74 100 5.97
Concrete 495.67 429.05 87 31.6
Total 93 37.57 77
69. Chief Engineer Narmada Tapti Basin, Indore Water Resources Division Dewas NA Sindhni Restructuring of Sindhani Project On Going DEW-8 18.06 13/09/2012 13/09/2013 Sindhani WUA Earthwork 18088 14288 79 1.71
Concrete 235.59 228.32 97 9.77
Total 88 11.48 64
70. Chief Engineer Narmada Tapti Basin, Indore Water Resources Division Dewas NA Koop Tank Dam Restucturing of Koop Project On Going DEW-11 42.9 22/10/2012 30/08/2013 Koop WUA Concrete 468 468 100 44
Earthwork 10839 10839 100 0
Total 100 44 103
71. Chief Engineer Narmada Tapti Basin, Indore Water Resources Division Dewas NA Padliya Tank Restucturing of Padliya Project On Going DEW-12 28.91 12/12/2012 11/10/2013 Chidawad WUA Earthwork 28979.38 32843 100 0
Concrete 404.76 107.14 26 19.84
Total 63 19.84 69
72. Chief Engineer Narmada Tapti Basin, Indore Water Resources Division Dewas NA Satbarli Satbarli Tank On Going DEW-25 18.1 01/10/2013 30/09/2014 Nagda WUA Concrete 103 80 78 0
Earthwork 16910 14600 86 11.08
Total 82 11.08 61
73. Chief Engineer Narmada Tapti Basin, Indore Water Resources Division Dewas NA Siya Siya Tank On Going DEW-24 22.89 01/10/2013 30/09/2014 Sindhani WUA Earthwork 22585 16224 72 0
Concrete 179 105 59 14.57
Total 65 14.57 64
74. Chief Engineer Narmada Tapti Basin, Indore Water Resources Division Mandsaur NA Ghatonda Construction of Restructuring & Mordanization Work of Ghatonda Tank Complete MAN-44 51.69 20/05/2014 19/07/2016 Dedaram Concrete 473.04 175 37 7.34
Lining all type 434 455 100 11.52
Pitching 4963.36 4963 100 17.06
Earthwork 35448 32300 91 12.06
Total 82 47.98 93
75. Chief Engineer Narmada Tapti Basin, Indore Water Resources Division Mandsaur NA Takrawad Restructuring & Mordanization work of Dhabla Dewal and Takrawad tank Complete MAN-35 113.52 20/05/2013 19/05/2015 Mahendra Jain Lining all type 276 1510 100 0
Earthwork 69608 50987 73 30.36
Concrete 1576 1576 100 48.37
Pitching 2964 2964 100 12.5
Total 93 91.23 80
76. Chief Engineer Narmada Tapti Basin, Indore Water Resources Division Neemuch NA Kundaliya Tank Kundaliya Tank Complete NEE-14 26.6 04/03/2014 03/12/2014 Kundaliya WUA Concrete 41.41 31 75 0.8
Others 6021.4 2400 40 1.01
CNS 2069.08 940 45 1.95
Masonary 34 34 100 0.75
Lining all type 1730 700 40 6
Earthwork 1444.56 1400 97 1.3
Total 66 11.81 44
77. Chief Engineer Narmada Tapti Basin, Indore Water Resources Division Shajapur NA BHANIYAKHEDI Dam BHANIYAKHEDI Dam Complete SHA-32 36.2 02/07/2013 01/04/2014 RANTHABHANWAR WUA Earthwork 12672 14500 100 20.97
Concrete 458.38 448 98 3.54
Total 99 24.51 68
78. Chief Engineer Narmada Tapti Basin, Indore Water Resources Division Shajapur NA Borsali Borsali Complete SHA-28 15.32 04/10/2013 03/12/2014 RANTHABHANWAR WUA Earthwork 15476 14700 95 10.83
Concrete 103 0 0 0
Total 47 10.83 71
79. Chief Engineer Narmada Tapti Basin, Indore Water Resources Division Shajapur NA Kheda new Kheda new Complete SHA-27 46.75 04/10/2013 03/12/2014 RANTHABHANWAR WUA Concrete 74.7 80 100 0
Earthwork 12288 17900 100 39.5
Total 100 39.5 84
80. Chief Engineer Narmada Tapti Basin, Indore Water Resources Division Shajapur NA Kheda old Kheda old Complete SHA-26 32.86 04/10/2013 03/12/2014 RANTHABHANWAR WUA Earthwork 18403 18040 98 0
Concrete 244.58 210 86 26.93
Total 92 26.93 82
81. Chief Engineer Narmada Tapti Basin, Indore Water Resources Division Shajapur NA Polaikhurd Tank Polaikhurd Tank Complete SHA-31 17.53 04/10/2013 03/12/2014 RANTHABHANWAR WUA Concrete 30.46 0 0 0
Earthwork 12601 11100 88 8.7
Total 44 8.7 50
82. Chief Engineer Narmada Tapti Basin, Indore Water Resources Division Shajapur NA Ranthbhanwar Ranthbhanwar Complete SHA-29 21.25 04/10/2013 03/12/2014 RANTHABHANWAR WUA Earthwork 3752 4800 100 19.15
Concrete 193 193 100 0
Total 100 19.15 90
83. Chief Engineer Narmada Tapti Basin, Indore Water Resources Division Shajapur NA Burlai Restructering of BURLAI Tank Project Complete SHA-21 83.98 05/03/2014 04/06/2015 Gyasiram Kushwah Gwalior Concrete 875 805 92 78.14
Earthwork 41000 40200 98 0
Total 95 78.14 93
84. Chief Engineer Narmada Tapti Basin, Indore Water Resources Division Shajapur NA Baorikheda Dam Restructuring of Baorikheda Tank On Going SHA-20 85.24 14/08/2013 13/04/2015 Agrawal Construction Co.,Bhopal Concrete 1376 1190 86 0
Earthwork 33000 32600 99 68.68
Total 93 68.68 81
85. Chief Engineer Narmada Tapti Basin, Indore Water Resources Division Shajapur NA Semlichacha Semlichacha Complete SHA-30 22.93 04/10/2013 03/12/2014 RANTHABHANWAR WUA Concrete 108.94 95 87 0
Earthwork 12526 9850 79 8.41
Total 83 8.41 37